Documents Checklist

Documents Required for a DPL License (Form L and Form M)

The same core papers are needed for a Form L licence (bulk tanks) and a Form M licence (drums in a godown). Keep clear copies ready, and make sure the owner named on the land papers is the same person whose CNIC you submit.

Land Requirement

Plot 120 Feet × 120 Feet, Minimum

A 120 ft × 120 ft plot is the practical minimum for a DPL storage godown. It fits a 30 ft × 30 ft godown in the centre with 45 ft of clear open space on all four sides, which covers the safety distance, vehicle movement and fire brigade access. If your plot is smaller, check it with us before you buy or build.

Sample Site Plan, 120 ft × 120 ft Plot

A 30 ft × 30 ft godown placed in the middle of the plot, with 45 ft of clear open space on all four sides: front, back, left and right. Your actual approved plan (5 copies) is prepared by our engineers to Explosives Department specification.

DPL plot plan 120 ft x 120 ft with 30 ft x 30 ft godown, 2 ft deep sump and 45 ft clear space on all sides

Why 120' × 120' Minimum?

It's Not Just the Building

Chemicals & Capacity on Final License

What Your License Actually Shows

Important Note, Construction Responsibility

We strongly recommend that construction is done by our own team. If the godown is built by others and the dimensions or specifications do not meet Explosives Department requirements, the result is: inspection failure, demolition and re-work, project delays of months, and expenses that were never visible in the original quote.

When we take responsibility, we construct it ourselves, and we do it properly. One team, one quote, one responsibility: the plot is verified, the plan is approved, the godown is built exactly to specification, and the license is granted, with no hidden costs and no blame-shifting between contractor and consultant.

  • Plot dimensions verified before any money is spent
  • Plan approved by Explosives Dept before construction starts
  • Built to pass inspection the first time, sump, ventilators, doors, fire systems
  • Single transparent quote, construction + license together
  • If we build it, we guarantee the license inspection
  • No plot? Use our rental godowns, already compliant
Storage Capacity

How the Storage Capacity of a Godown Is Calculated

The godown floor is built as a sump 2 ft deep, so any leak or spill stays inside the godown. The storage capacity is worked out from the sump volume, and one cubic foot holds 28.31 litres.

Safety Distance by Quantity (Petroleum Class A)

Licensed quantity in the godownClear distance to protected works
Up to 2,500 litres6 m (about 20 ft)
2,500 to 25,000 litres7.5 m (about 25 ft)
25,000 to 50,000 litres9 m (about 30 ft)
50,000 to 100,000 litres12 m (about 40 ft)
Above 100,000 litres15 m (about 50 ft)

Petroleum Class B and Class C need shorter distances. Where different classes are stored together, the whole quantity counts as the most flammable class. Our 30 ft × 30 ft example holds 48,410 litres, which needs 9 m (about 30 ft), and the 120 × 120 ft plot leaves 45 ft on every side.

Keep Reading

Related Licensing Guides

Land Requirements for DPL Storage License in Pakistan

One of the most common, and most expensive, mistakes in the DPL process is buying or leasing a plot that is too small. The minimum acceptable plot for a chemical storage godown license is 120 feet × 120 feet. This is the practical minimum: a smaller plot cannot accommodate the required safety distances, vehicle movement area, and fire brigade access, and the storage license will simply not be granted.

Check Before You Buy

Send us your plot details, dimensions, location, and surroundings, before you commit. Our free plot assessment confirms whether the land can be licensed, whether any gas main lies within 50 feet, and whether the District Authority NOC is obtainable at that location. Five minutes of checking can save you from buying unusable land.

Your Final License Lists Every Chemical with Its Capacity

The granted DPL license is not a general permission, it itemizes each chemical by name with its licensed storage capacity. Planning this list correctly at application time matters: under-license and your business is restricted; over-license and you pay unnecessary fees. We build your chemical-and-capacity schedule with you, backed by MSDS for each product, so the final license matches your real business needs.

Land survey for petrol pump site requirements in Pakistan
Common Questions

Land Requirements FAQs

What documents are required for a DPL license in Pakistan?
Paper of land, NTN certificate, CNIC copy of the owner named on the land papers, accounts maintenance certificate, Memorandum and Articles of Association, company registrations, a site drawing with dimensions, the total storage quantity and its purpose, and details of your government affiliations. The same set is used for Form L and Form M.
Multiply length × width × 2 ft sump depth × 28.31 litres. A 30 ft × 30 ft godown gives 50,958 litres. After leaving 5% air space, about 48,410 litres is declared on the licence.
For a standard storage godown license, no, the minimum dimensions are required for safety distances and access. Your options are: acquire an adjacent plot to meet the minimum, or use our DPL-ready rental godowns which already meet all requirements. Contact us and we’ll assess your specific situation.
Yes, through a license amendment filed with the Department of Explosives, new MSDS and updated fees apply. We handle amendments, and our renewal tracking clients often combine amendments with their annual renewal to save time.
Because the license depends on the construction. When one team is responsible for both, there is no gap: the sump depth, ventilator placement, door specification, and dimensions are built exactly as the approved plan requires, and the inspection passes the first time. When we take the responsibility, we construct it, and we guarantee the result with one transparent quote.

Check Your Plot Before You Spend

Free plot assessment, dimensions, location, NOC feasibility, and a transparent construction + license quote.

Scroll to Top